My 2nd week at YTL , i was posted on duty supervising another site from the same double track railway project here's some preview on it.
Pile Load Test - My Sub-Contractors are basically beneath that huge gigantic rocks ( FYI : 300 Tonnes ) for 72 hours continuous taking readings from the gauge installed beneath it and i am suppose to check out their recorded that to ensure there is no cheating and the calculations are correct...imagine if that thing collapsed..~scary~
Sentul Site Office
Gauges and jack installed beneath the pile load test
Piling at the Sentul Station - tricky work cause we might cause the trail to derailed