Field Density Test to check the degree of compaction of the soil
1.my railway bridge ....inspecting the reinforced bars for the slab so it is placed properly according to drawing
2.monitoring the the casting of concrete for the slab.
3.the third pic is reinforcing bars for parabet after casting of the slab.
Reinforced bars for precast post-tensioned U-beam (box girder)
1 .Excavation to expose the piles than to be hacked to expose the starter bars for pilecap
2. Hacking of excess concrete of the pile so that Pile Integrity Test (PIT) can be done to test the pile still in good shape or not before the pile cap is placed
3. PIT test
4. Formwork for the pile cap
5.This what a pilecap looks like beneath it consists of 3 bored piles with starter bars attached to it
6. After the pilecap, ...there goes the pier goin up ...as u all see in those highways.
No comments:
Post a Comment